29 October 2024

In Transit - July 1998 - No. 93 - Flood damage and summary of state highway funding under 1999 National Roading Programme

The July 1998 edition of InTransit primarily focused on repairs to flood damaged highways in Taranaki, Waikato, Bay of Plenty, Auckland and Northland.  However, it also included a summary of state highway funding under the 1999 National Roading Programme, funded by Transfund NZ at the time.

Highlights were:

  • $444.2m of funding for the year for Transit NZ for all of its work, around half of all funding going to Transit NZ, the remainder going to local authorities for local roads and public transport.
  • $221m of Transit's funding was for state highway maintenance
  • The funding threshold for new projects was maintained at a BCR of 4:1. 
  • Projects separated into Category 1 (approved now) and Category 2 (funding approved dependent on finalising resource consents, property purchases).
New projects with approved funding were listed by region, with those mentioned (that were not already committed) including:
  • Design of Grafton Gully upgrade on SH16
  • Structural upgrade of Auckland Harbour Bridge to meet seismic standards
  • Development of ATMS on Auckland's motorway network
  • SH2 Sargants Corner realignment, Hauraki District
  • SH5 Rotorua Stockpile Curves realignment
  • SH3 Awakino realignment
  • Four-laning of Old Taupo Road Rotorua (SH5)
  • Route J, Tauranga (SH2)
  • White Pine Bush South realignment SH2, Hastings District
  • Glengarry Hill realignment SH5, Hastings District
  • SH3A South Clearview Curves realignment, New Plymouth District
  • Urenui Bridge replacement SH3, New Plymouth District
  • Investigation/planning for SH1 4-laning, realignment from Plimmerton to Pukerua Bay, Porirua City
  • Maisey-Bronte realignment SH60, Tasman District
  • Candy's Bend to Starvation Point realignment, SH73
  • SH1 Hawkswood Deviation near Cheviot
  • Six single-lane bridge widenings SH6 Makaroa
  • SH1 Gore Main Street improvements
  • SH1 Fairfield Motorway Dunedin (extension of Southern Motorway beyond Green Island)








23 October 2024

In Transit - March 1998 - No. 89 - Mobile phone dangers and preparation needed for major state highway projects

The March 1988 edition of InTransit highlights the growing dangers of mobile phone use on road safety, noting a paper to be delivered at a forthcoming conference reporting "mobile-phone users who make more than three calls per trip have nearly three times as many injury accidents and twice as many fatal accidents as those who never use a mobile phone".

At the time the then Land Transport Safety Authority noted that there were more crashes due to people lighting a cigarette or adjusting a car stereo than a mobile phone, but of course the numbers of the public with mobile phones in 1998 were still relatively modest.  A smaller article on the second page notes a Canadian paper that mobile phone use increases driving danger as much as drunk driving.  In 1998 there was no specific offence in New Zealand of driving whilst using a mobile phone.

Other notable articles in this edition are:

  • A major project update noting progress on the following projects:
    • Stage One Kamo Bypass, SH1, Whangarei (subsequently completed)
    • Orewa Bridge replacement, SH1 Rodney District (completed the following month)
    • Albany-Silverdale (ALPURT), SH1 Auckland, construction contracts let, resource consents sought for Silverdale to Puhoi (subsequently discontinued as the project was reprioritised and redesigned to be a toll road).
    • Mercer-Cambridge four laning (later dubbed the Waikato Expressway). Designations sought for Mercer to Ohinewai, and corridor options being considered for Ohinewai to Cambridge. At the time it was thought the project would be completed in 2010, but was completed in 2022.
    • Kopu Bridge replacement, SH25. Expected to be completed 2002, it was actually completed 2011.
    • Hawke's Bay Motorway (later Expressway). Pakowhai to Hastings under construction, the York Road  (bypassing Hastings) extension under design. Full completion expected 1999 (which was true for those sections, but the final extension south was not completed until 2011).
    • Vinegar Hill realignment, SH1 Manawatu. Under construction and was completed 1999
    • Newlands Interchange, SH1 Wellington, under construction and completed late 1998
    • Thorndon Motorway Viaduct seismic strengthening SH1, Wellington, under construction and completed 1999 (images included in this edition).
    • Stoke Bypass, SH6 Nelson. Work commenced and would be completed on schedule in 2000.
    • Otira Viaduct, SH73 Canterbury, Work underway and concluded in 1999
    • Fairfield Bypass SH1 Dunedin, Route designation and resource consent applications lodged. Project would be completed in 2003.
  • Success of the Thorndon motorway viaduct seismic strengthening project, designed to ensure it can survive a 1 in 500 year earthquake of up to seven on the Richter scale.
  • Article describing the process (in 1998) of developing a major highway project before construction could begin, the stages being:
    • Strategic planning
    • Investigation
    • Design
    • Planning approval
    • Land purchase
    • Construction
  • Transit NZ adopting new standards on road lighting.










18 October 2024

In Transit - December 1997/January 1998 - No. 87 - Installation of skid retardant surface near Petone

This edition of In Transit, highlights the successful installation of a new skid retardant surface under the Petone over bridge on SH2 near Wellington.  The new surface was credited with a 100% drop in crashes over seven months.  The new product, called Safe Grip, created 40% more friction.

Other stories in this edition include:

  • Photos depicting the installation of the overbridge at the Newlands Interchange on SH1 in Wellington 
  • Photo of turning the sod on the Pakowhai to Hastings section of the "Hawke's Bay Motorway" (now called the Hawke's Bay Expressway noting it is one lane each way).
  • List of roadworks underway over Christmas/New Year.
  • Presentation from Malaysia about privatising the countries toll road network.





26 September 2024

In Transit - June 1997 - No. 81 - Annual safety certification of highways, Newlands Interchange and other projects

 The June 1997 issue of In Transit had articles on the following points:

  • An annual safety certification of the state highway network is to be produced to identify opportunities to improve the safety of the network. This covers factors like roadside shoulder slopes, road camber, obstructions on the road edge, running a checklist over the entire network, with annual reviews of this status.
  • Retirement of John Kearney from the Transit NZ Board. He commented that establishment of Transit NZ improved control and management of the state highway system, as it looked at it from a system not a sectoral point of view. 
  • Work commencing on the $16.5m Newlands Interchange project in Wellington on SH1.
  • Near completion of a new level crossing at Rolleston with Selwyn District, adjacent to SH1 (a site of four fatalities).
  • Vibralines to be installed on the edges of Auckland motorways following successful trials on the Johnsonville-Porirua Motorway near Tawa. This is expected to reduce the 400 accidents a year due to vehicles running off the motorway network, by cutting injury crashes by 15%.
  • Transit NZ purchased land as part of a property development north of Tauranga to enable a corridor for the future northern Tauranga arterial project (what is now known as Takitimu North Link).
  • Options being investigated for the Te Puke Bypass (what is now the Tauranga Eastern Link) SH2.
  • Work to start on the $7m Kaitoke realignment on SH2 Wellington between Upper Hutt and the Remutakas.
  • Joint planning study launched with Kapiti Coast District Council for what was to be called the Kapiti Western Link Road project (a local road to connect Raumati, Paraparaumu and Waikanae to relieve SH1). This project was cancelled in favour of the Kapiti Expressway which was started in 2013 and completed in 2017, bypassing Paraparaumu and Waikanae with SH1.












18 September 2024

In Transit - February 1997 - No. 78 - Focus on repairs after Cyclones Fergus and Drena

 


In NZ, emergency works were always not too far away as part of the portfolio of works for road networks.  In February 1997, Cyclones Fergus and Drena caused extensive damage mainly in the Coromandel District.  The feature article highlights the cost of $5.8m (1997 prices) to fix the damage on SH25 and SH2, but also damage on SH1 (Brynderwyns), SH35 and SH88.

Other stories include:
  • Review of Special Purpose Roads: Special Purpose Roads were a category of local road that were subject to higher Financial Assistance Rate funding (typically 75%) from the National Roading Programme compared to other local roads (which obtain typically 50%). Such roads get higher funding because of a high proportion of tourist traffic, be below state highway standard and pass by properties with rating potential much lower than the costs of maintaining the road.  Curiously, this decision has mostly funding implications, yet was being carried out by Transit New Zealand which was no longer the funding agency, as Transfund New Zealand had been formed the previous year. 
  • Declaration of the revoked section of SH38 as a Special Purpose Road: As part of the State Highway Review in 1995, Transit New Zealand revoked SH38 between Te Whaiti and Ruatahuna. Transit announced it had decided to classify it as a Special Purpose Road increasing the funding to 75% of maintenance costs. That section of road was not sealed at the time. 
  • Earthquake strengthening of Thorndon Overbridge of the Wellington Urban Motorway: Image provided of the work to strengthen the 72 concrete columns supporting the Wellington Urban Motorway from the harbour over the Ferry Terminal, railway yards, Thorndon Quay. 
  • Briefing to the incoming Minister of Transport - Jenny Shipley indicates critical traffic levels in Auckland: This noted that traffic on Auckland Harbour Bridge had increased 20% between 1989 and 1997, and on the Northern Motorway south of Albany (when at this time it terminated), it had doubled from 1989 to 1995.  It noted work was underway investigating and consulting on various major projects included:
    • SH1 Albany-Puhoi (built in two stages)
    • SH1 Harbour Bridge approaches (subsequently cancelled in favour of the Victoria Park Tunnel)
    • SH18 Greenhithe Bypass (built as part of the Upper Harbour Motorway)
    • SH18 Hobsonville Bypass (built as part of the Upper Harbour Motorway)
    • SH20 extension to Richardson Road (built)
    • SH20 extension to SH1 south (built)
    • Bus only lanes on Northern Motorway (partially replaced with Northern Busway)
  • Transit NZ winning the Institution of Professional Engineers New Zealand (IPENZ) environmental award: For the upgrade of SH12 through Waipoua Forest.





29 January 2024

Upper Hutt's River Road - a story of mismanagement causing death

In March 1987 Upper Hutt welcomed the long-awaited Upper Hutt bypass, which was quickly named as "River Road" to take SH2 away from the long, slow, traffic signal stopped drive through Silverstream, Heretaunga, Trentham, Wallaceville and Upper Hutt along Fergusson Drive, to a new fast route, at state highway speeds, following the Hutt River to Moonshine Rd, then crossing to the east side of the river to connect at Maoribank.  The road was one of the last major highway projects in the Wellington region commissioned by the National Roads Board (NRB), which was an arm of the Ministry of Works & Development (MWD).  In 1989 these functions would be transferred to a new Crown entity called Transit New Zealand, which would be state highway manager and land transport funder, and the MWD would be reformed into a state-owned enterprise, which would be later split and privatised in 1996. The motivation behind these reforms is a part of this story.

The new road not only saved considerable time for through traffic from the Wairarapa through to Lower Hutt and Wellington, but also better connected the western suburbs of Upper Hutt, and removed a great deal of heavy traffic from Fergusson Drive, where it interacted with pedestrians, cyclists and created safety hazards and generated pollution for the city.  Ultimately it opened up new areas for housing west of the river at what is now known as Riverstone Terraces.

However, the road was built at a deliberately low cost.  It had sign and traffic signal controlled intersections, rather than grade-separated ones.  The Moonshine Road intersection placed immediately north of the bridge was particularly poorly designed (and has since been relegated to having access to/from the highway southbound only).

Despite having a 100km/h limit, the new Moonshine Bridge was built to a 70 km/h design standard, creating an awkwardly tight bend for highway traffic around halfway along the route. It also was not built with any passing lanes, a problem which became clear soon after it was opened, as motorists complained about being stuck behind trucks, but also motorists who would stop along the route to sightsee or park by the river.  

The MWD had a solution. It did not have the funding (which at the time was part of the annual budgeting process of the Minister of Finance) to widen the road for passing lanes at the conventional highway lane width standard of 3.5 metres.  The road had been built with one 3.5 metre lane in each direction, and with sealed shoulders.  So it was decided as a quick fix, to fashion passing lanes between Silverstream and Moonshine Bridge within the pre-existing sealed carriageway, by removing the sealed shoulder so that an additional lane could be marked out.  This was done, but had several major problems:

  • The lane widths were narrowed to be 3m not 3.5m
  • The passing lane taper lengths were shorter than the usual standard
  • The speed limit remained the same
  • No median barriers, let alone painted median was installed.
The effect of building these narrow, short lanes, was devastating and a series of fatal accidents occurred over several months.  Seven people were killed in four accidents in four months.  The fatalities would continue. 

Ultimately funding was granted in the following year to widen the road so that the passing lanes were built to a proper standard, widened and lengthened.  Some years later a median barrier was installed.  It was notable that in 1988 the new Chair of the National Roads Board and Minister of Transport was also local MP, Bill Jefferies.  He would subsequently preside over reforms that meant he would not be involved in picking the projects to be funded, and to set up Transit New Zealand as a professional Crown agency a a dedicated state highway manager and land transport funder. In parallel, the MWD would be split and would have to compete with private contractors for state highway construction work. 

The clipping below highlight the celebrations on the opening of the bypass, and one article reporting the death toll and calls to upgrade the road.












24 January 2024

In Transit - August 1996 - No. 75 - 18% increase in state highway spending and Transfund separates from Transit

The August 1996 issue of In Transit is the first edition of the Transit NZ newsletter to be published after the agency's funding functions were transferred to Transfund NZ.  This issue focused primarily on the state highway funding provided by the 1996 National Roading Programme.  Key highlights of that were:

  • 18% increase in state highway funding compared to the previous year
  • New projects to be funded include:
    • Hastings extension of the 2-lane Napier-Hastings Motorway (bypassing Pakowhai to terminate on the outskirts of Hastings). This would later be redesignated as the "Hawke's Bay Expressway" and see SH2 relocated to this route.
    • Stoke Bypass SH6 Nelson
    • Albany-Silverdale extension to the Auckland Northern Motorway as the first stage of the ALPURT project
    • Otira Viaduct SH73 Canterbury to bypass the treacherous zig-zag section in Arthurs Pass
  • BCR threshold for project funding had been lowered from 5 to 4.5 and was expected to be 4 the following year
The newsletter also notes that the split between Transfund and Transit means "Transit can focus its energies on being the national manager of the state highway network". It was noted it would enable the agency to focus more on its professional expertise including development of a state highway strategy, so that the network was developed in a co-ordinated way.

Other points in the newsletter included:
  • Progress in the State Highway Review (which reviews which roads should or should not be State Highways). Noting that the Review proposed revoking State Highway status for SH1 from the entrance of the Port of Bluff to the southern tip due to the lack of tourist traffic
  • Colder weather explaining more closures of Desert Road (noting postponement of a trial of using road salt)
  • Various conferences
In Transit August 1996 p1
In Transit August 1996 p2
In Transit August 1996 p3

In Transit August 1996 p4

29 November 2023

1996 National Roading Programme: Waikato/BOP NRP news

The Waikato/Bay of Plenty regional spending for the 1996 National Roading Programme had the following main statistics:

  • $99.47m for Waikato. State Highway maintenance and construction spending was the main output class, with 50% of spending. 
  • $44.44m for the Bay of Plenty. State Highway maintenance and construction spending was the main output class, with 51% of spending.
Main increases for state highway spending were for additional reseals, additional pavement rehabilitation and additional road markings.

Safety projects of note were:

  • Hamilton City arterial street lighting upgrade
  • Rotokauri Street safety improvements, Hamilton City
  • SH2 Sargents Corner realignment 
  • SH27 Maukoro Landing Road intersection upgrade
  • SH5 Tarukenga Curves Stage 2 realignment
  • SH5 Tumunui South realignment
  • 32.3km of seal extension throughout both regions
No new state highway construction projects were approved because of the high value of committed works, and all but two local road construction projects were seal extension projects. The seal extension projects were in Otorohonga District, Waitomo District, Opotiki District, Western Bay of Plenty District and Whakatane District.

Committed major projects included:
  • SH1 Pokeno Bypass (extension of Waikato Expressway)
  • SH1 Mangatawhiri Bridge realignment (part of Waikato Expressway)
  • Hamilton City Pukete Arterial Stage 1
  • SH2 Church-Timber Mill
  • SH25 Kuaotunu Hill seal extension
  • SH25 Coromandel-Whangapoua seal extension
  • SH5 Earthquake Flats realignment

Transfund NRP news Hamilton Office 1996 p1



Transfund NRP news Hamilton Office 1996 p2



Transfund NRP news Hamilton Office 1996 p3

Transfund NRP news Hamilton Office 1996 p4



Transfund NRP news Hamilton Office 1996 p5


Transfund NRP news Hamilton Office 1996 p6

28 November 2023

1996 National Roading Programme: Hawke's Bay/Gisborne NRP news

The 1996 National Roading Programme Napier regional office newsletter covers funding for the Hawke's Bay and Gisborne regions.  The primary focus for new work was local road seal extensions.

New construction projects funded included:
  • Hawke's Bay Expressway (then called Motorway) extension enabling works Hastings to Pakowhai
  • SH5 Beatties to Marshalls realignment
  • East Cape Road seal extension 10km, Gisborne District
  • Anaura Road seal extension 2.2km, Gisborne District
  • Mangatu Road seal extension 4km, Gisborne District
  • Mill/Lawn roundabout construction, Hastings District
  • Napier-Taihape Road seal extensions, Hastings District
  • Tangoio Road seal extension, Hastings District
  • Kahuranaki Possum Bridge replacement, Hastings District
  • Stardust (Mill) Bridge replacement, Napier Road, Hastings District
  • Mohaka Township Road seal extension, Wairoa District
  • Tiniroto Road seal completion (5km), Gisborne District
Also funded were major design projects including:
  • Hawke's Bay Expressway Omahu-York Road (Hastings to Flaxmere)
  • White Pine Bush S. Realignment, SH2
  • King's Woolshed Realignment SH2
  • Glengarry Hill Realignment SH5








27 November 2023

1996 National Roading Programme: Manawatu/Taranaki NRP news

The 1996 National Roading Programme Wanganui regional office newsletter covers funding for the Manawatu and Taranaki regions. Key statistics were:

  • $53.3m for the Manawatu region and $18.6m for the Taranaki region.
  • Largest output class for the Manawatu was local road maintenance and construction at 40.5% of spending
  • Largest output class for the Taranaki region was state highway maintenance and construction at 41.1% of spending
Major committed projects included:
  • SH4 Laurence's Dropout
  • SH3 Maxwell to Bushy Park upgrade
  • SH57 Laws Hill realignment
  • FItzherbert Avenue 4-laning in Palmerston North City
New construction projects funded included:
  • 7.6km seal extension on SH43 Moki Tunnel
  • SH3 realignment Mimi Curves
  • SH1 Vinegar Hill realignment ($5.1m)
  • SH43 Tahora Flats seal extension of 2.3km
  • SH1 realignment south of Waiouru railway crossing
  • SH2 Bradleys realignment south of Dannevirke
  • SH3 Grants Hill corner realignment
  • SH4 Waihapa curves easing




23 November 2023

1996 National Roading Programme: Wellington NRP news

 The Wellington regional newsletter of the 1996 NRP has the following key statistics:

  • $62m for the Wellington region
  • $26.9m for the Nelson/Marlborough/Tasman districts
  • For the Wellington region, state highway maintenance and construction is the largest output class comprising 34.9% of spending. Passenger transport was 25.4% of spending as the second largest output class.
  • For Nelson/Marlborough/Tasman, state highway maintenance and construction was also the largest output class at 55.2% of spending
Unlike Christchurch, the Wellington newsletter contained little detail, noting the following committed projects:
  • SH58 Judgeford realignment
  • SH1 Newlands Interchange
  • SH2 Gibbons Street seagull roundabout Upper Hutt
New projects funded included:
  • SH6 Stoke Bypass, Nelson (the largest road project in the region)
  • SH1 Basin Reserve traffic signals
  • SH1 Paraparaumu widening
  • SH60 reconstruction between Maisey and Bronte
  • SH1 Thorndon motorway viaduct further strengthening 
  • SH6 Spooners Hill passing lane
  • Mungavin Bridge duplication, Porirua