Transfund News - November 1996 - No.3 - Working with local authorities and Alternatives to Roading

 The third edition of Transfund News in 1996 had no major focus, but included articles as follows:

  • Additional funding for territorial authorities to meet the costs of former State Highways that would be redesignated as local roads by Transit New Zealand under the latter's state highway review. The purpose being so that territorial authorities are able to more gradually absorb the local share of costs of roads that are no longer state highways, through other funding sources notably rates increases.
  • Development of Partnership Agreements between Transfund and road controlling authorities and regional councils, to formalise the funding arrangements between them.
  • Competition for construction contracts has been strong, with an average of 4.1 responses for each contract put out for tender by Transit NZ and territorial authorities for road physical works. It was noted that the Competitive Pricing Procedures in 1995 had resulted in a 10-15% reduction in state highway maintenance and construction costs.  Competitive tendering would continue to be rolled out so that by 1998 all minor and ancillary work would be put out to tender.
  • Local Authority Trading Enterprises (LATEs) won one in six local road physical works contracts in the first six months of 1996.  LATEs (now known as commercial Council Controlled Organisations) were the former local authority works departments that were required to be restructured into trading enterprises for local authorities to be able to receive central government funding for road works (this was intended to ensure a level-playing field between council and private contractors).  At the time, Manukau City, Waitomo District, New Plymouth District, Hastings District, Central Hawke's Bay District, Dunedin City and Clutha Districts had LATEs that won such contracts. 
  • Transfund released a discussion document called "Financial Assistance for Alternatives to Roading". It was split into public transport and freight ATRs. The purpose was to recognise that in the absence of road pricing, the land transport system would not be efficient if it only funded roads, if there was infrastructure or services that could be funded to make up the difference between user contribution and the net benefit of the project.  Two key constraints for ATR funding were significant. One was that funding was only available for projects that met the same benefit/cost ratio threshold as road projects that were being funded (in 1996 that was 4.5/1), another was that benefits were primarily benefits to road users as they were the ones paying for the project.
  • Concern about unsafe objects located around road networks, which Transfund can only provide guidelines and recommendations about.
Transfund News November 1996 No. 3 p1
Transfund News November 1996 No. 3 p2

Transfund News November 1996 No. 3 pg3

Transfund News November 1996 No. 3 pg4


01 February 2024

Transfund News - September 1996 - No. 2 - focus on new funding procedures

The second edition of Transfund News followed its first National Roading Programme and contained the following articles:

  • Release of Transfund's first Programme and Funding Manual listing all output classes, work categories and policy changes from when Transit NZ was the funding agency.  Key elements included incorporating safety fully into the capital works outputs, and for road maintenance to be  single output class across state highways and local roads. 
  • Launch of Transfund. Chairman Michael Gross noted that it "removed any potential conflict of interest" in funding.  It also included a dedicated roading fund (as it meant RUC and a portion of fuel excise duty would be hypothecated, and not reliant on the usual annual Budget process) for the first time, providing security of funding for capital and maintenance funding. Also noted was the ability to fund "efficient alternatives to roading". 
  • Removal of First Year Rate of Return as a funding criteria element, as increases in funding no longer rendered it necessary to ration project funding.  This was a measurement of the proportion of benefits a project would generate in its first year, compared to later years, as an additional element to determine whether a project which met the benefit/cost ration threshold had a higher priority for funding over others.
  • Contracts will be created between Transfund and Transit NZ, territorial authorities and regional councils for funding granted to them.  This reflects Transfund's role as purchase of services on behalf of road users and the desire to ensure good performance. 
  • Strong response to discussion paper on funding "efficient alternatives to roading", with final evaluation procedures to be decided at the end of the year.
  • Funding proposal procedures to be tightened.  This followed a report that indicated 34% of projects reviewed had significant shortcomings in their Benefit/Cost Ratio calculations.. Road controlling authorities are to be required to undertake peer reviews of their calculations. 
  • New software enables quicker calculation of benefits for projects that reduce accident costs

Transfund News September 1996 No.2 pg1
Transfund News September 1996 No.2 pg2

Transfund News September 1996 No.2 pg3


Transfund News September 1996 No.2 pg4








24 January 2024

In Transit - August 1996 - No. 75 - 18% increase in state highway spending and Transfund separates from Transit

The August 1996 issue of In Transit is the first edition of the Transit NZ newsletter to be published after the agency's funding functions were transferred to Transfund NZ.  This issue focused primarily on the state highway funding provided by the 1996 National Roading Programme.  Key highlights of that were:

  • 18% increase in state highway funding compared to the previous year
  • New projects to be funded include:
    • Hastings extension of the 2-lane Napier-Hastings Motorway (bypassing Pakowhai to terminate on the outskirts of Hastings). This would later be redesignated as the "Hawke's Bay Expressway" and see SH2 relocated to this route.
    • Stoke Bypass SH6 Nelson
    • Albany-Silverdale extension to the Auckland Northern Motorway as the first stage of the ALPURT project
    • Otira Viaduct SH73 Canterbury to bypass the treacherous zig-zag section in Arthurs Pass
  • BCR threshold for project funding had been lowered from 5 to 4.5 and was expected to be 4 the following year
The newsletter also notes that the split between Transfund and Transit means "Transit can focus its energies on being the national manager of the state highway network". It was noted it would enable the agency to focus more on its professional expertise including development of a state highway strategy, so that the network was developed in a co-ordinated way.

Other points in the newsletter included:
  • Progress in the State Highway Review (which reviews which roads should or should not be State Highways). Noting that the Review proposed revoking State Highway status for SH1 from the entrance of the Port of Bluff to the southern tip due to the lack of tourist traffic
  • Colder weather explaining more closures of Desert Road (noting postponement of a trial of using road salt)
  • Various conferences
In Transit August 1996 p1
In Transit August 1996 p2
In Transit August 1996 p3

In Transit August 1996 p4

30 November 2023

1996: National Roading Programme: Auckland/Northland NRP news

 The Auckland/Northland newsletter for the 1996 National Roading Programme of Transfund NZ.

It was noted that 46% of spending in Auckland was road maintenance.  The newsletter has a comprehensive list of all state highway and local road projects funded, including investigation and design in Auckland and Northland. Notable in this NRP was approval of funding for the extension of the Northern Motorway from Albany to Silverdale, which continued to Orewa until funding to proceed was suspended in the early 2000s until tolling was authorised for the Orewa to Puhoi section. Investigation and design also began for a series of other major motorway projects in Auckland, including extensions of SH16 and the Upper Harbour Motorway SH18.

Major committed projects included:

  • SH16 Northwestern Motorway Rosebank and Patiki Rd Interchange construction
  • SH20 Southwestern Motorway extension Quarry Rd (Mangere Bridge) to Massey Rd (Papatoetoe), connecting the Mangere Bridge to the Pupatoetoe Bypass, and towards the Airport to George Bolt Memorial Drive
  • Auckland City Southeastern Arterial (Church Street-Mt Wellington-Pakuranga Motorway).

New construction projects included:

  • SH1 Northern Motorway extension Albany to Silverdale
  • SH1 Auckland Harbour Bridge seismic upgrade
  • SH1 Orewa Bridge replacement (pre Silverdale-Puhoi extension of Northern Motorway)
  • SH1 Puhoi-Wellsford passing lanes
  • 16km of seal extensions in Rodney District
  • Wairau Road intersection upgrades in North Shore
  • Thirteen seal extension projects in Far North District
  • Eight seal extension projects in Whangarei District

New investigation and design work was funded for future projects:

  • SH1 Warkworth-Dome Alley improvements
  • SH1 Schedewys Bypass
  • SH1 St Marys Bay/Victoria Park Viaduct widening/tidal flow (this did NOT proceed and was replaced by the Victoria Park Tunnel)
  • SH16 Northwestern Motorway Brighams Creek extension
  • SH18 Upper Harbour Motorway
  • SH20 Southwestern Motorway extension Hillsborough to Dominion Road
  • SH1 Southern Motorway Greenland Interchange upgrade
  • SH1 Southern Motorway Otahuhu Interchange upgrade
  • Auckland ATMS
  • Orewa Link Road to connect to Silverdale-Puhoi extension of Northern Motorway



Transfund NRP news Auckland Office pg1

Transfund NRP news Auckland Office pg2


Transfund NRP news Auckland Office pg3
Transfund NRP news Auckland Office pg4


Transfund NRP news Auckland Office pg5

Transfund NRP news Auckland Office pg6

Transfund NRP news Auckland Office pg7

Transfund NRP news Auckland Office pg8

29 November 2023

1996 National Roading Programme: Waikato/BOP NRP news

The Waikato/Bay of Plenty regional spending for the 1996 National Roading Programme had the following main statistics:

  • $99.47m for Waikato. State Highway maintenance and construction spending was the main output class, with 50% of spending. 
  • $44.44m for the Bay of Plenty. State Highway maintenance and construction spending was the main output class, with 51% of spending.
Main increases for state highway spending were for additional reseals, additional pavement rehabilitation and additional road markings.

Safety projects of note were:

  • Hamilton City arterial street lighting upgrade
  • Rotokauri Street safety improvements, Hamilton City
  • SH2 Sargents Corner realignment 
  • SH27 Maukoro Landing Road intersection upgrade
  • SH5 Tarukenga Curves Stage 2 realignment
  • SH5 Tumunui South realignment
  • 32.3km of seal extension throughout both regions
No new state highway construction projects were approved because of the high value of committed works, and all but two local road construction projects were seal extension projects. The seal extension projects were in Otorohonga District, Waitomo District, Opotiki District, Western Bay of Plenty District and Whakatane District.

Committed major projects included:
  • SH1 Pokeno Bypass (extension of Waikato Expressway)
  • SH1 Mangatawhiri Bridge realignment (part of Waikato Expressway)
  • Hamilton City Pukete Arterial Stage 1
  • SH2 Church-Timber Mill
  • SH25 Kuaotunu Hill seal extension
  • SH25 Coromandel-Whangapoua seal extension
  • SH5 Earthquake Flats realignment

Transfund NRP news Hamilton Office 1996 p1



Transfund NRP news Hamilton Office 1996 p2



Transfund NRP news Hamilton Office 1996 p3

Transfund NRP news Hamilton Office 1996 p4



Transfund NRP news Hamilton Office 1996 p5


Transfund NRP news Hamilton Office 1996 p6

28 November 2023

1996 National Roading Programme: Hawke's Bay/Gisborne NRP news

The 1996 National Roading Programme Napier regional office newsletter covers funding for the Hawke's Bay and Gisborne regions.  The primary focus for new work was local road seal extensions.

New construction projects funded included:
  • Hawke's Bay Expressway (then called Motorway) extension enabling works Hastings to Pakowhai
  • SH5 Beatties to Marshalls realignment
  • East Cape Road seal extension 10km, Gisborne District
  • Anaura Road seal extension 2.2km, Gisborne District
  • Mangatu Road seal extension 4km, Gisborne District
  • Mill/Lawn roundabout construction, Hastings District
  • Napier-Taihape Road seal extensions, Hastings District
  • Tangoio Road seal extension, Hastings District
  • Kahuranaki Possum Bridge replacement, Hastings District
  • Stardust (Mill) Bridge replacement, Napier Road, Hastings District
  • Mohaka Township Road seal extension, Wairoa District
  • Tiniroto Road seal completion (5km), Gisborne District
Also funded were major design projects including:
  • Hawke's Bay Expressway Omahu-York Road (Hastings to Flaxmere)
  • White Pine Bush S. Realignment, SH2
  • King's Woolshed Realignment SH2
  • Glengarry Hill Realignment SH5








27 November 2023

1996 National Roading Programme: Manawatu/Taranaki NRP news

The 1996 National Roading Programme Wanganui regional office newsletter covers funding for the Manawatu and Taranaki regions. Key statistics were:

  • $53.3m for the Manawatu region and $18.6m for the Taranaki region.
  • Largest output class for the Manawatu was local road maintenance and construction at 40.5% of spending
  • Largest output class for the Taranaki region was state highway maintenance and construction at 41.1% of spending
Major committed projects included:
  • SH4 Laurence's Dropout
  • SH3 Maxwell to Bushy Park upgrade
  • SH57 Laws Hill realignment
  • FItzherbert Avenue 4-laning in Palmerston North City
New construction projects funded included:
  • 7.6km seal extension on SH43 Moki Tunnel
  • SH3 realignment Mimi Curves
  • SH1 Vinegar Hill realignment ($5.1m)
  • SH43 Tahora Flats seal extension of 2.3km
  • SH1 realignment south of Waiouru railway crossing
  • SH2 Bradleys realignment south of Dannevirke
  • SH3 Grants Hill corner realignment
  • SH4 Waihapa curves easing




23 November 2023

1996 National Roading Programme: Wellington NRP news

 The Wellington regional newsletter of the 1996 NRP has the following key statistics:

  • $62m for the Wellington region
  • $26.9m for the Nelson/Marlborough/Tasman districts
  • For the Wellington region, state highway maintenance and construction is the largest output class comprising 34.9% of spending. Passenger transport was 25.4% of spending as the second largest output class.
  • For Nelson/Marlborough/Tasman, state highway maintenance and construction was also the largest output class at 55.2% of spending
Unlike Christchurch, the Wellington newsletter contained little detail, noting the following committed projects:
  • SH58 Judgeford realignment
  • SH1 Newlands Interchange
  • SH2 Gibbons Street seagull roundabout Upper Hutt
New projects funded included:
  • SH6 Stoke Bypass, Nelson (the largest road project in the region)
  • SH1 Basin Reserve traffic signals
  • SH1 Paraparaumu widening
  • SH60 reconstruction between Maisey and Bronte
  • SH1 Thorndon motorway viaduct further strengthening 
  • SH6 Spooners Hill passing lane
  • Mungavin Bridge duplication, Porirua




22 November 2023

1996 National Roading Programme: Canterbury/West Coast NRP news

The Canterbury/West Coast Transfund newsletter highlighted spending in the first National Roading Programme issued by Transfund New Zealand. Key statistics included:
  • $49.24m to be spent in Canterbury
  • $22.91m to be spent in the West Coast
  • Local road maintenance and construction was the largest output class for Canterbury at 36.2% of spending.  Passenger transport was 7.2% of spending
  • State highway maintenance and construction was the largest output class for the West Coast at 58.4% of spending.
Projects of significance on state highways included:
  • Otira Viaduct on SH73. Cost of $26.1m to bypass the "zigzag" section and multiple slip and earthquake prone sections of highway, significantly improving resilience on the route.
  • Craigieburn Bridge replacement on SH73 at $0.63m, replacing a single lane bridge with a history of accidents.
  • Washdyke Bridge replacement on SH1 at $0.63m, which was an old two-lane stone bridge bottleneck on a three-lane section of highway.
  • Additional passing lanes north of Rakaia overbridge, SH1
Projects of significance on local roads included:
  • Rolleston railway crossing replacement, removing a dangerous level crossing that was the site of the infamous Southerner accident.
  • Seven cycleway improvements in Christchurch City
  • Committed improvements to the intersection of Moorhouse Avenue, Madras Street and Manchester Street in Christchurch City
  • 1km seal extension on Inland Kaikoura Route in Kaikoura District
Unlike the Dunedin regional office newsletter, this newsletter contains detailed lists of projects approved, across State Highways 1, 73 and 6 and local road projects in Christchurch City, Hurunui District, Timaru District, Waimakariri District and Grey District.







21 November 2023

1996 National Roading Programme: Otago/Southland NRP news

1996 was Transfund New Zealand's first National Roading Programme, after it had been set up that year to be an independent land transport funding agency.

It issued a series of newsletters outlining the major projects funded in each region. This is the one published by the Dunedin regional office covering Otago and Southland. 

Key statistics were:

  • $45.72m to be spent in Otago. Local road spending was the largest at around 44.5%.
  • $22.72m to be spent in Southland. Local road spending was the largest category also at around 44.5%
Significant committed works with ongoing funding included the seal extension on Glenorchy Road in Queenstown-Lakes District and three bridge replacement works on local tourist roads.

New projects highlighted were:
  • 5km further seal extension on the "Southern Scenic Route" (Catlins) in the Clutha District.
  • Seal extension of the southern section of St Bathans Loop Road in Central Otago.
NRP news 1996 Dunedin office


NRP news 1996 Dunedin office

16 November 2023

Transfund News No. 1 July 1996 - National Roading Programme

This the very first edition of Transfund news following the launching of the Crown agency as the dedicated land transport funding agency, separated from Transit New Zealand (which remained as the state highway manager).  The edition was understandably focused on the 1996/1997 National Roading Programme, Transfund's first. It had previously been called the National Land Transport Programme reflecting funding for both roads and public transport, but the new emphasis was to reflect Transfund's role as essentially a purchaser of road maintenance and improvements, and public transport services, on behalf of motorists.

 Key elements were:

  • $743.7m ($1.45b in 2023 prices) in total spending for the year (compared to $675.9m the previous year, a 10% increase).
  • The increase reflected a Budgetary increase of $122.9m over the subsequent three years.
  • The benefit/cost threshold for capital spending was reduced from 5:1 to 4.5:1 for the 1996/97 year and to 4:1 for the 1997/98 year. This reflected Government confidence in Transfund ensuring quality of spending and the general Budget entering surplus (enabling a greater proportion of fuel tax revenue to be directed to the National Roads Fund).
  • The three-year cap on passenger transport funding was removed.
  • Passenger transport funding was increased by $13.5m to replace funding removed due to abolition of regional fuel taxes.
  • Additional spending was otherwise focused on increased maintenance, minor safety projects, new state highway construction projects, bridge reconstruction, continuation of seal extension.
  • Major projects to start included:
    • Albany-Silverdale section of the Albany-Puhoi realignment (SH1 Northern Motorway)
    • Otira Viaduct SH73 Canterbury
    • Stoke Bypass SH6 Nelson
    • Orewa River Bridge Auckland
    • Thorndon motorway viaduct seismic upgrade SH1 Wellington
  • The newsletter contained a table comparing the previous year's spending by output class.


Transfund News July 1996 No.1 Pg1

Transfund News July 1996 No.1 Pg2

Transfund News July 1996 No.1 Pg3



Transfund News July 1996 No.1 Pg4

13 November 2023

Wellington traffic and transport funding woes in the 1990s

This post is a series of articles from 1990 through to 1999 discussing the issues and funding of roads and urban transport more generally in Wellington.


This article from 1990 reflects the cuts in funding in the last budget under the Fourth Labour Government, at the time under Geoffrey Palmer, which provided $153m less funding that Transit New Zealand sought.  Projects threatened (and delayed) were:

  • Korokoro/Petone upgrade to SH2 (which was not undertaken until the late 1990s)
  • Fergusson Drive median barriers Upper Hutt City (which did not proceed)
  • Cable Street extension Wellington (which did proceed to create the one-way system with Wakefield Street)
  • Ramp Bridge replacement Porirua, SH1 (which proceeded in the late 1990s.


This feature by Kate Coughlan in The Dominion describes the major traffic problems in Wellington in the 1990s.  It concludes that there is unlikely to be any significant relief. It summarises some of the issues of driving in the morning peak and follow by a map with traffic figures describing the main choke points. 



This summary is a fair report of the key traffic bottlenecks across the region in 1996.  To review where these now are in 2013:
  • Paremata-Pukerua Bay: The proposed solution at the time was implemented, with a second Paremata Bridge, clearways, traffic lights through to Plimmerton and four-laning through Plimmerton.  This relieved congestion at this location, but Pukerua Bay became the major bottleneck. This was addressed long-term with the Transmission Gully motorway, although the forecast it would be open by 2006 proved to be more than a decade out.
  • SH2:  In 1996 the problems were the intersections at Korokoro and Melling. The best solution mooted was the Cross Valley Link (which has not yet been built), but the proposed solution was grade separation at Korokoro, Dowse Drive and Melling.  Korokoro and Dowse Drive were built in the early 2000s, but Melling although funded is yet to commence construction.  In 2023, Melling remains a major bottleneck, but north of Manor Park, SH2 is particularly slow in the AM peak.
  • Mungavin Avenue: In 1996, the Mungavin Roundabout queued back to Cannons Creek. As reported, the solution was a duplicate Mungavin Bridge, which was built in 1998 and addressed the bottleneck.
  • Newlands lights:  The busiest traffic light controlled intersection on SH1 was a major bottleneck, but as reported, the Newlands Interchange had been funded and would permanently relieve this bottleneck. 
  • Wellington city motorway offramps: Not specific on the ramps, but noted that policy was to discourage car commuting into the CBD, and encourage public transport use by sustaining subsidies for rail and bus services.  This appears largely to have succeeded as traffic to the Wellington CBD in the AM peak has been flat for over 20 years.
  • Karori Road:  The Karori Tunnel and Karori Road were bottlenecks with very slow traffic at the time and this has not changed. The best solution at the time was said to be to widen Karori Road and duplicate the tunnel, but the expected solution was a bus lane.  The outcome was the Chaytor Street bus lane, which is soon to be removed to accommodate an uphill cycle lane under Let's Get Wellington Moving.  Karori Tunnel remains a bottleneck.
  • Mt Victoria Tunnel/Basin Reserve:  The 1996 bottleneck was traffic exiting Mt Victoria Tunnel to the Basin Reserve, and from Adelaide Road. The preferred solution was grade-separation at the Basin Reserve, but planned solution was traffic signals. In 2023, the Basin Reserve is a major bottleneck, as is the tunnel. 
  • Terrace Tunnel to Mt Victoria Tunnel: Congestion between the two tunnels was chronic in the 1990s with the dog-leg route between the tunnels.  The preferred solution was to duplicate the tunnels and connect them with the proposed cut-and-cover motorway extension. However, what was expected was the "Inner City Bypass" of Karo Drive with a one-way system. This was expected to be completed by 2000, but did not finish until 2007.  In 2023, the two tunnels are major bottlenecks, and Vivian Street/Karo Drive are regularly congested at peak times.
  • The Merge (SH2/SH1 Ngauranga): This was described as caused by incompetent driving and the solution was Police presence at the site encouraging better behaviour.  In 2023, the issue remains although northbound in the PM peak, the addition of a fourth lane from Aotea Quay has greatly eased congestion in that direction.
Evening Post 25 June 1996

Meanwhile, the Business Roundtable believed that the time was right to end public transport subsidies, and that the Wellington Regional Council should progressively reduce such subsidies and ensure services paid their own way, and allow more bus services to compete with rail. These proposals were not taken up.


The Evening Post editorial of 22 June 1996 focused on transport funding in Wellington, noting that the $930m wishlist of the Regional Council for roads and public transport would take 180 years to be funded, at the levels available at the time. At the time it included Transmission Gully, a major upgrade to the Rimutaka Hill Road and replacing the old electric multiple units with light rail.  It had proposed a tax on inner city carparks, which did not proceed. The Evening Post proposed that money directed from fuel tax to the Crown account be put into the National Roading Fund.  Ultimately this did happen, but not until after 2008. Subsequently Transmission Gully was funded, along with some upgrades to the Rimutaka Hill Road, but it was decided that light rail was not a viable replacement for the English Electric EMUs in Wellington, and Korean-built "Matangi" units. 

Evening Post 06 September 1996

The Wellington Regional Council transport committee discussed in 1996 the idea of putting a toll on SH1 Ngauranga Gorge to raise money to fund its proposed transport programme. Noting that the only elements of transport in Wellington it has authority to fund are public transport as it is not a road controlling authority.  The proposal would have charged $1 for traffic entering Wellington via the Ngauranga Interchange.  It received widespread opposition and no support from Government, and did not proceed.

Evening Post 22 June 1997


Trucking lobby group, the Road Transport Association (RTA) was highly critical of transport policies in Wellington in 1997, including the specific policy of not increasing the capacity of highways entering Wellington from the north.  Former Minister of Works and Chief Executive of the RTA, Tony Friedlander, was critical of the ruling out of extra capacity between Ngauranga and Petone (which at the time was planned to be a third southbound lane from Horokiwi to Ngauranga using the space of the current cycleway). This had been opposed by the Regional Council.  

The article also notes that trolley buses were to be phased out in five years (which did not occur for another 15 years), and the Wellington Regional Council wanted to tax carparks in Wellington, Hutt and Upper Hutt and Porirua cities.




The above article discussed proposals to four-lane Johnsonville Road from Ngauranga Gorge to the Moorefield Road roundabout.  The land was designated to enable widening, and was proposed to relieve congestion from through traffic adjacent to the retail precinct.  The proposal generated strong opinions in favour and against, but other options were also mentioned, including converting Johnsonville Road to a mall and building a new motorway interchange at Helston Road (to remove through traffic), both ruled out due to cost.  

Evening Post 30 April 1999

The Evening Post in 1999 reported on the draft Land Transport Strategy of the Wellington Regional Council, which was essentially its wishlist of road and public transport projects for the region. Statistics NZ reported that car commuting was falling across the region, with public transport patronage growing.  Proposed projects for roads were:
  • Kapiti Western Link Road (not built, replaced by Kapiti Expressway)
  • Mackays Crossing overbridge (built in the early 2000s)
  • Transmission Gully (completed in 2022)
  • Pauatahanui Bridge upgrade (completed in late 1990s)
  • SH1 improvements Paremata-Pukerua Bay (completed in early 2000s)
  • Rimutaka Hill Road upgrades (some completed in 2010s)
  • Kaitoke realignment (completed in 2000s)
  • SH58/SH2 interchange (completed in 2016)
  • Petone Esplanade upgrade (not undertaken)
  • SH2 Petone-Ngauranga bus lane (not undertaken)
  • Karori bus lane (completed in late 1990s)
  • Inner City Bypass and Adelaide Road upgrade (Stage 2 bypass completed 2007, Adelaide Road upgrade did not proceed)
Public transport projects proposed were:
  • Electrification to Waikanae (completed 2011)
  • Raumati station (never built)
  • Upgrades to Petone, Upper Hutt and Paraparaumu stations
  • Porirua to Hutt bus service (trialled in 1990s but cancelled due to lack of patronage)
  • Bus priority signals and lanes in central Wellington (lanes built)
  • New bus-rail interchange at Wellington station (built in 2000s)
  • Pedestrian covers in central Wellington streets (some built in 2000s)
The Regional Council also proposed light rail from Plimmerton to Whitby (which has not proceeded), between Melling and Waterloo stations (which has not proceeded) and to investigate light rail from Wellington station to the BNZ centre (southern end of Lambton Quay) (the latter is proposed as part of Let's Get Wellington Moving, but extended to Island Bay). 

Evening Post 30 June 1998 and 26 April 1999

These two articles reflect actual funding provided in 1998 and the Wellington Regional Council's proposed Land Transport Strategy in 1999. 

The 1998 article noted that the 1998-1999 National Roading Programme reduced funding for Wellington by 25% from the previous year, although total funding nationally increased by 6.2%.  The reason being that fewer construction work was funded for the 1998-1999 year, because of most of the completion of the Newlands Interchange.  Future construction projects were in the investigation and design stage, specifically the Dowse Drive/Korokoro upgrade on SH2, Kapiti Western Link Road, Karori bus lane and the Daly St extension to Queens Drive, Hutt City.  It was expected those projects would start the following year, but the first two did not.  Funding was provided for completion of the Newlands Interchange. Thorndon motorway viaduct earthquake strengthening, Kapiti Rd SH1 intersection upgrade.

 The article on the right saw the WRC propose to be undertaken between 1999 and 2004:
  • Bus lane on SH2 from Horokiwi to Ngauranga (did not proceed in favour of upgrading cycle lane)
  • Fourth lane on the Urban Motorway from Ngauranga to Aotea Quay with movable median barrier (did not proceed due to technical difficulties)
  • Korokoro-Dowse Drive upgrade/interchange (completed late 2000s)
  • Upgrade to Rimutaka Hill Road (Wellington side largely completed)
  • Stage 2 Inner City Bypass (opened 2007)
It also proposed projects to be undertaken beyond 2004:
  • Transmission Gully (opened 2022) said to cost $245m
  • Kapiti Western Link Road (superseded by Kapiti Expressway) estimated at $24m
  • Hutt to Porirua link road (not built and not pursued) estimated at $62m
  • Upgrading Petone Esplanade (not built)
  • Melling and Kennedy Good Interchanges (Melling funding approved in 2022) estimated at $33m