23 October 2024

In Transit - March 1998 - No. 89 - Mobile phone dangers and preparation needed for major state highway projects

The March 1988 edition of InTransit highlights the growing dangers of mobile phone use on road safety, noting a paper to be delivered at a forthcoming conference reporting "mobile-phone users who make more than three calls per trip have nearly three times as many injury accidents and twice as many fatal accidents as those who never use a mobile phone".

At the time the then Land Transport Safety Authority noted that there were more crashes due to people lighting a cigarette or adjusting a car stereo than a mobile phone, but of course the numbers of the public with mobile phones in 1998 were still relatively modest.  A smaller article on the second page notes a Canadian paper that mobile phone use increases driving danger as much as drunk driving.  In 1998 there was no specific offence in New Zealand of driving whilst using a mobile phone.

Other notable articles in this edition are:

  • A major project update noting progress on the following projects:
    • Stage One Kamo Bypass, SH1, Whangarei (subsequently completed)
    • Orewa Bridge replacement, SH1 Rodney District (completed the following month)
    • Albany-Silverdale (ALPURT), SH1 Auckland, construction contracts let, resource consents sought for Silverdale to Puhoi (subsequently discontinued as the project was reprioritised and redesigned to be a toll road).
    • Mercer-Cambridge four laning (later dubbed the Waikato Expressway). Designations sought for Mercer to Ohinewai, and corridor options being considered for Ohinewai to Cambridge. At the time it was thought the project would be completed in 2010, but was completed in 2022.
    • Kopu Bridge replacement, SH25. Expected to be completed 2002, it was actually completed 2011.
    • Hawke's Bay Motorway (later Expressway). Pakowhai to Hastings under construction, the York Road  (bypassing Hastings) extension under design. Full completion expected 1999 (which was true for those sections, but the final extension south was not completed until 2011).
    • Vinegar Hill realignment, SH1 Manawatu. Under construction and was completed 1999
    • Newlands Interchange, SH1 Wellington, under construction and completed late 1998
    • Thorndon Motorway Viaduct seismic strengthening SH1, Wellington, under construction and completed 1999 (images included in this edition).
    • Stoke Bypass, SH6 Nelson. Work commenced and would be completed on schedule in 2000.
    • Otira Viaduct, SH73 Canterbury, Work underway and concluded in 1999
    • Fairfield Bypass SH1 Dunedin, Route designation and resource consent applications lodged. Project would be completed in 2003.
  • Success of the Thorndon motorway viaduct seismic strengthening project, designed to ensure it can survive a 1 in 500 year earthquake of up to seven on the Richter scale.
  • Article describing the process (in 1998) of developing a major highway project before construction could begin, the stages being:
    • Strategic planning
    • Investigation
    • Design
    • Planning approval
    • Land purchase
    • Construction
  • Transit NZ adopting new standards on road lighting.










30 November 2023

1996: National Roading Programme: Auckland/Northland NRP news

 The Auckland/Northland newsletter for the 1996 National Roading Programme of Transfund NZ.

It was noted that 46% of spending in Auckland was road maintenance.  The newsletter has a comprehensive list of all state highway and local road projects funded, including investigation and design in Auckland and Northland. Notable in this NRP was approval of funding for the extension of the Northern Motorway from Albany to Silverdale, which continued to Orewa until funding to proceed was suspended in the early 2000s until tolling was authorised for the Orewa to Puhoi section. Investigation and design also began for a series of other major motorway projects in Auckland, including extensions of SH16 and the Upper Harbour Motorway SH18.

Major committed projects included:

  • SH16 Northwestern Motorway Rosebank and Patiki Rd Interchange construction
  • SH20 Southwestern Motorway extension Quarry Rd (Mangere Bridge) to Massey Rd (Papatoetoe), connecting the Mangere Bridge to the Pupatoetoe Bypass, and towards the Airport to George Bolt Memorial Drive
  • Auckland City Southeastern Arterial (Church Street-Mt Wellington-Pakuranga Motorway).

New construction projects included:

  • SH1 Northern Motorway extension Albany to Silverdale
  • SH1 Auckland Harbour Bridge seismic upgrade
  • SH1 Orewa Bridge replacement (pre Silverdale-Puhoi extension of Northern Motorway)
  • SH1 Puhoi-Wellsford passing lanes
  • 16km of seal extensions in Rodney District
  • Wairau Road intersection upgrades in North Shore
  • Thirteen seal extension projects in Far North District
  • Eight seal extension projects in Whangarei District

New investigation and design work was funded for future projects:

  • SH1 Warkworth-Dome Alley improvements
  • SH1 Schedewys Bypass
  • SH1 St Marys Bay/Victoria Park Viaduct widening/tidal flow (this did NOT proceed and was replaced by the Victoria Park Tunnel)
  • SH16 Northwestern Motorway Brighams Creek extension
  • SH18 Upper Harbour Motorway
  • SH20 Southwestern Motorway extension Hillsborough to Dominion Road
  • SH1 Southern Motorway Greenland Interchange upgrade
  • SH1 Southern Motorway Otahuhu Interchange upgrade
  • Auckland ATMS
  • Orewa Link Road to connect to Silverdale-Puhoi extension of Northern Motorway



Transfund NRP news Auckland Office pg1

Transfund NRP news Auckland Office pg2


Transfund NRP news Auckland Office pg3
Transfund NRP news Auckland Office pg4


Transfund NRP news Auckland Office pg5

Transfund NRP news Auckland Office pg6

Transfund NRP news Auckland Office pg7

Transfund NRP news Auckland Office pg8

02 November 2023

National Land Transport Programme 1996 - Northland newsletter

 

National Land Transport Programme 1996 National funding

National Land Transport Programme 1996 Northland summary

National Land Transport Programme 1996 Northland summary allocations



National Land Transport Programme 1996 Northland Local Roads funding



National Land Transport Programme 1996 Northland State Highway funding



A few months ago I posted the newsletters for other regions for the 1996 National Land Transport Programme (see Auckland, Wellington, Waikato, Gisborne/Hawke's Bay, Taranaki/Manawatu,  Canterbury, Otago/Southland), this is the newsletter for Northland region.

$50.4m was allocated to the region for the year, 47% of funding was provided to local roads, 52% to state highways and the remainder to public transport and administration (public transport being almost entirely funding paratransit services).

Key projects noted were:
  • Funding to complete sealing of SH12 through Waipoua, as the last portion of state highway in Northland that was unsealed
  • 82km of local roads in Far North District were sealed in the previous year, the programme continued into the following year with 24 new seal extension projects
  • Nine new seal extension projects on local roads in Whangarei District
  • Realignment of SH1 north of Hukerenui
  • Urlich Hill relignment on SH10
  • Brynderwyn North widening on SH1
  • Kamo Bypass design